See Traffic Plan for Detour to be in place. Hancock Drive Businesses will remain open and accessible.
Week of Monday, January 12, 2026
The Force Main will be installed alongside and north of McCullom Lake Road between the intersection of E. Wonder Lake Road (North Leg) and Hancock Drive/Mc Cullom Lake Road (at the three way stop intersection) to about one mile east at the Village Waste Water Treatment Plant (Blue Tank with Village of Wonder Lake on its side on the south side of the Road).
Periodically, throughout the 7 am to 5 pm workday, the two-way traffic on McCullom Lake Road will be reduced to one-way traffic that will be controlled by Flaggers. Please follow the directions from the Flaggers and be prepared to stop when approaching or in the Work Area.
Week of Monday, January 19, 2026
The Force Main will be installed alongside and north of McCullom Lake Road between the intersection of E. Wonder Lake Road (North Leg) and Hancock Drive/Mc Cullom Lake Road (at the three way stop intersection) to about one mile east at the Village Waste Water Treatment Plant (Blue Tank with Village of Wonder Lake on its side on the south side of the Road).
Periodically, throughout the 7 am to 5 pm workday, the two-way traffic on McCullom Lake Road will be reduced to one-way traffic that will be controlled by Flaggers. Please follow the directions from the Flaggers and be prepared to stop when approaching or in the Work Area.
The previously scheduled work to close the intersection of E. Wonder Lake Road (North Leg) and Hancock Drive/McCollum Lake Road (at the three-way stop intersection) for force main and sanitary sewer installation has been postponed to a time to be determined.