Week of June 8, 2026
The Contractor will be installing topsoil, grass seed and blanket in the parkway along select locations of E Wonder Lake Road (between Hancock Drive/McCullom Lake Road (at the three-way stop intersection) to 500 feet north of Center Drive), and McCullom Lake Road (Area noted below).
The topsoil, grass seed and blanket will be installed alongside and north of McCullom Lake Road between the intersection of E. Wonder Lake Road (North Leg) and Hancock Drive/Mc Cullom Lake Road (at the three way stop intersection) to about one mile east at the Village Waste Water Treatment Plant (Blue Tank with Village of Wonder Lake on its side on the south side of the Road).
Periodically, throughout the 7 am to 5 pm workday, the two-way traffic on McCullom Lake Road will be reduced to one-way traffic that will be controlled by Flaggers. Please follow the directions from the flaggers and be prepared to stop when approaching or in the Work Area.